Case Studies
SAPERA Energy Management Service
SAPERA is a proven & systematic approach to understanding your energy landscape through data analytics, supported by engineering and project delivery expertise…
Thermal Reconfiguration
This audit identified several projects which could reduce the site carbon emissions through improving the thermal generation efficiency of the plant. The…
Free Cooling HVAC
Installation of two mixing Air Handling Units with CHW & LPHW coils and upgrades to the existing HVAC infrastructure. Annual chillers thermal…
Boiler House of the Future: Food & Nutrition Client
The expansion of manufacturing required additional utility capacity for the site. The system was upgraded focusing on energy efficient design. The overall…
Heat Recovery Extension
Heat Recovery project consisting of the Installation of new LPHW boiler system including new BFW preheater heat exchanger, modifications to the existing…
Air Compressor Upgrade: Pharmaceutical Client
The expansion of manufacturing required additional utility capacity for the site. The system was upgraded focusing on energy efficient design. Improvements were…
Thermal Equipment Upgrade: Food Client
The new boilers were sized with consideration for the future expansion, and to allow for possible downtime of the new LPHW system…
CHP & LPHW
New energy efficient CHP units, LPHW boilers & optimized the existing BFW system.CHP (Cogeneration) is an energy efficient technology that generates electrical…
Steam Boilers
This end of life replacement project implemented energy efficiency design throughout the project to focus on CO2 reduction and financial savings. Steam…
LPHW System Project
To a new mCHP (Micro co-generation) system and the separation of LPHW Generation and Process steam in the pharma building. Delivering this…
Heat Recovery Project (RHI Scheme)
Heat Recovery Project with payback of 2.43 years. The aim of this project was to provide water heating form alternativesources to steam…
Global Solutions Lab Cooling
Free Cooling System with the payback of 1.24 years. Datacentres energy intensive facilities that have significant potential to make use of efficiency…
Air Compressors
The expansion of manufacturing required additional utility capacity for the site. The system was upgraded focusing on energy efficient design. Improvements were…
Heat Recovery Project
Heat Recovery Project with 3.28-year paybackHeat pumps utilize the refrigeration cycle. Instead of dumping heat to atmosphere as any chiller would, the…
Heat Recovery & Thermal Reconfiguration
The plant used large quantities of steam to heat hot water. Hot water is used for cleaning, Domestic Hot Water (DHW) and…